BACKFLOW BASE

Backflow Base / Tester certification / Test procedures

Backflow test procedures, step by step.

How we recommend performing each step of the field test for the certification exam, based on the requirements in the USC Tenth Edition test procedures.

Last updated .

Before you test: N.I.I.O.

Notify, Identify, Inspect and Observe, in that order, before a hose goes on. Each assembly's page adds what is specific to it.

Notify

Identify

Inspect

Observe

TC is a test cock. SOV is a shut-off valve. psid is pounds per square inch, differential.

Assemblies

What passes

RPZ
Relief valve opens at 2.0 psid or more. #1 check holds 5.0 psid or more, above the relief opening. #2 check is tight against backpressure.
Double check
Each check holds 1.0 psid or more.
PVB
Air inlet opens at 1.0 psid or more. Check holds 1.0 psid or more.
SVB
Check holds 1.0 psid or more. Air inlet opens at 1.0 psid or more.

The software

Contact

hello@backflowbase.com